Electrical and plumbing mistakes are the most expensive errors in a home, not because they are hard to fix technically, but because they are buried in walls and floors under plaster, tiles and marble. A wrong cable size or drain slope during first fix can mean breaking out a whole room after you move in. Here are the mistakes we see most often in Jeddah villas and apartments, and how to check that your MEP first fix is right before it is closed up.
Electrical mistakes
1. Undersized cables
The classic false economy: 2.5 mm² cable for an AC that needs 4 mm², or an oven on a general socket circuit. The result is hot cables, nuisance tripping and, at worst, insulation burning inside the wall. Jeddah's AC units run long hours at high load, which multiplies the risk.
| Use | Indicative cable size | Indicative breaker |
|---|---|---|
| Lighting circuits | 1.5 mm² | 10 A |
| General socket circuits | 2.5 mm² | 16 – 20 A |
| Mid-size split AC | 4 mm² | 20 – 32 A by rating |
| Water heater | 2.5 – 4 mm² | 20 – 25 A |
| Electric oven or cooker | 6 mm² | 32 A |
These are common indicative values, not a design. Final sizes depend on load, run length, installation method and the Saudi Building Code.
2. Missing or cosmetic earthing
Earthing protects people from electric shock when a metal appliance develops a fault. We sometimes find earth wires run to sockets but never connected to a real earth electrode, or an electrode whose resistance was never measured. Insist on a properly installed earth rod with an inspection pit, a recorded earth resistance test, and a continuous earth conductor to every socket, metal fitting and appliance.
3. A poorly planned distribution board
- Too many circuits on one breaker, or two AC units sharing a circuit.
- No labelling.
- No spare capacity (we suggest around 20-30%).
- No 30 mA RCD protection for bathrooms, kitchens, garden and pool.
- Unbalanced loads across the three phases.
4. Sockets and switches in the wrong places
Sockets hidden behind kitchen units, switches behind an opening door, nothing beside the bed. Approve a furniture layout before first fix, especially for kitchens, bedrooms and majlis.
5. Ignoring smart-home pre-wiring
Even if you are not installing a smart system now, prepare for it:
- A neutral at switch boxes (many smart switches need one).
- Spare empty conduits between the DB, floors and roof.
- Cat6 data cabling to main rooms, ceiling Wi-Fi points and cameras.
- Power points for motorised curtains, gates and outdoor lighting.
Plumbing mistakes
6. No pressure test
The most serious plumbing mistake. Seal the water network, pump it above working pressure (usually at least 1.5 times) and watch the gauge for several hours up to 24 hours with no drop, before plastering and tiling. A weak joint should show up now, not a year later as a damp patch on your majlis marble.
7. Wrong drain slopes
Drains work by gravity: roughly 2% for 2-3 inch pipes and about 1-2% for 4 inch and larger. Too little fall causes deposits and blockages; too much lets water outrun solids. Floors that pond around the drain after tiling are a common symptom.
8. Missing traps and vents
Every fixture and floor drain needs a trap holding a water seal against sewer gases, and the system needs vent pipes up to the roof, otherwise pressure changes empty the traps, causing smells and gurgling.
9. PVC on hot water lines
| Material | Correct use | Notes |
|---|---|---|
| PPR | Hot and cold water supply | Heat-fused, handles heat and pressure; use the right class for hot water |
| uPVC | Drainage, rainwater, vents | Solvent-welded; not for pressurised hot water |
| HDPE | External and buried water lines | Flexible, tough, fusion-welded |
Ordinary PVC on heater lines deforms and leaks at joints within a few years. Wet areas also need waterproofing with a flood test before tiling, an essential step in any kitchen and bathroom finishing job.
Pre-plaster checklist
- Approved electrical and plumbing drawings, and work matching them.
- Cable sizes per the design schedule; conduits not crushed.
- Earth resistance test recorded.
- Labelled DB with spare ways and RCDs for wet areas.
- Passed, dated water pressure test.
- Measured drain slopes, traps and vents for every fixture.
- PPR for supply, uPVC for drainage.
- Photos of every wall before closing, for future reference.
To see where this fits in the overall build, read our guide to house construction stages. If you are planning ducted AC, see our villa AC systems guide, since its power and condensate lines are part of the same first fix.
Key takeaway
Saving money on MEP first fix is a false saving. The price difference for a bigger cable or better pipe is trivial compared with breaking out marble and gypsum later. Invest in correct drawings, approved materials, documented tests and engineering supervision before anything is closed.
How Alfa can help
At Alfa for Decor & Contracting we deliver electrical, plumbing and HVAC works as part of our MEP services, with clear drawings, approved materials and documented pressure and earthing tests in line with the Saudi Building Code, plus smart-home pre-wiring on request. Contact us for a free consultation and site visit to review your first fix before it is closed.
FAQ
What are the most common electrical mistakes in villas?
Undersized cables, missing or untested earthing, too many circuits on one breaker, unlabelled distribution boards with no spare ways, and no 30 mA RCD protection for bathrooms, kitchens and outdoor circuits.
What cable size does a split AC or water heater need?
As a guide, mid-size wall-mounted AC units are commonly wired with 4 mm² cable, water heaters with 2.5-4 mm² depending on rating, and electric ovens with 6 mm². The engineer should confirm sizes based on load, run length, installation method and code requirements.
How is a water pipe pressure test done?
The network is sealed and pumped to a pressure above working pressure, usually at least 1.5 times, then the gauge is monitored for several hours up to 24 hours with no drop. It must be done before plastering and tiling.
Is PPR better than PVC?
They serve different purposes. PPR is for hot and cold water supply because it handles heat and pressure and is heat-fused, while uPVC is for drainage, rainwater and vents. Using PVC on hot water lines is a common cause of leaks.
Why do bathroom floor drains smell?
Usually a missing or dried-out trap, or no vent pipes so pressure changes siphon water out of the traps. Proper trapped drains, a vented system and topping up unused drains solve it.